October 21, 2008

Got Pecans!

Filed under: Pecan Farming — knewman @ 9:24 am

A lot has been happening at the pecan grove!  First, an update on the senior residence.  The builder has given us a date when they’ll be finished… January 31, 2009.  Later than we’d hoped, but realistic.  The brick and stone are being laid now. The electrical and plumbing are well along.  It should be ready for insulation and sheet rock in a few weeks.  The 7 acre lake in front of the senior residence has been drained down so we can dredge out silt that has built up over the years, so it’s ugly now!  We have a very disappointed beaver somewhere.

We have one (of the possible 10) apartments spoken for already, and we’re receiving significant interest from other possible residents, so hopefully we’ll have some several moving in when we open in February.

Our neighbor, Glynn, finally agreed to sell us his place, so Jack and Leona will move into Glynn’s place in November.  This reduces the number of houses we need to build. Glynn is a master gardener, and has a very nice garden, which Kathy and Kim hope to maintain.  Here are a few pictures of Glynn’s place.  We’ll make a few changes before Jack and Leona move in.

Awhile back we were able to purchase the 10 acres in the front center of the property, so now it is all one piece.  The picture below (taken before we purchased the place) shows the boundary of the property in red.  The yellow lines are overhead power lines.  The light blue is the road into the farm, senior residence and Mike and Ronda’s place.  The dark blue will be a driveway over to Jack and Leona’s place.

Good progress has been made on the house for Mike and Ronda.  Here are some pictures.

Finally, the pecans are in!  The steps in the pecan harvesting process are:

  1. Shake the pecan tree with a shaker causing the pecans (and sometimes squirells) to fall to the ground.
  2. Use a harvester to pick the pecans up off the ground
  3. Use a cleaner to separate the leaves, sticks, etc. from the pecans
  4. Dry the pecans by spreading them out on a drying table (or drying them in bags)
  5. Crack them in a cracker.
  6. Separate the meat from the shell in a separator
  7. Separate most of the shells from the meat in a blower
  8. Run the meat across a vibrating table while people pick out remaining pieces of shell
  9. Sort the meat by size – full halves and broken pieces.

Pictures of some of these machines and some pecans are shown below.

September 19, 2008

Hurricane Ike

Filed under: Pecan Farming — knewman @ 5:16 pm

The center of the eye of hurricane Ike passed just a few miles east of the pecan grove.  The residence itself received very little damage… some tar paper was blown off the roof.

The two porta potties for the construction crews didn’t fair as well!

There was damage to the pecan trees, but not nearly as bad as we expected.  A few were destroyed by splitting.  About 25 others were blown over.  We’ve pulled these back up with the tractor and tied them to adjacent trees… they should be ok.

Of the 5 types of pecans we have, the Pawnees are the first to be harvested, usually in the first 2 weeks of October.  Many of the Pawnee pecans were blown from the trees.  We’ve picked a lot of them up and find that they are good to eat, though a little premature.  The following picture shows some Pawnees emerging from their husk.

There was other damage… some of which could be easily fixed…

And some cannot!

The residents found this whole experience very stressful….

For pictures from around our house see the newman family blog in the menu at the top right.

Ken

August 24, 2008

Lots of Progress

Filed under: Pecan Farming,Pecan Grove,Rosamond Residence,Senior Residence — knewman @ 6:25 pm

We returned from Paris yesterday and went out to see the progress at the pecan grove this afternoon.  Most of the plywood is on the roof of the Sr. residence, and all the studs are up.

 

Mike and Ronda’s house is coming along well.  It’s “dried in” now, and is scheduled to be done in October.

Many of the pecan trees are loaded with pecans.  The photo below shows a cluster of 7 pecans.  Some of the trees are breaking due to the heavy load of fruit.  One tree, show below, has split so bad it will need to be cut off and grafted again, so only the strong root will be saved. 

Some of the trees have grown slowly and have no fruit.  Mike pulled some of these up and found that their tap root was growing in circles (see below).  Young trees are started in buckets and the tap root is forced to grow in a circle.  When the tree is removed from the bucket and planted, this root must be cut and the little that remains will usually straighten and go straight down.  Evidently when these trees were planted this wasn’t done, so they have no depth of root, and cumber the ground.  Unfortunately, we have quite a few trees that will have to be cut down… no amount of digging around them and fertilizing them would help.

Ken

 

August 4, 2008

Upward and onward

Filed under: Senior Residence — knewman @ 10:18 pm

 

Carpenters have been busy putting the wall puzzle togther.  It goes fast and neat when they’re all built offsite.

Walls are plumbed and aligned by Saturday.  Roof trusses are delivered and await a crane to help set them in place.

 

 

The well is complete with pump and tank set and just needs electrical power to pump water on demand.  We tried a generator but it takes a lot of juice. 

 

The drive to Jack and Leona Newman’s site got a culvert in the creek so heavy trucks can cross.  The drill truck showed up to take a sample of the soil where the house pad will be.

 

The local electric company finally got us in their schedule and looks like they’re serious about getting us some power.  Equipment and materials are stocked for underground service installation. 

The Rosamond residence is waiting on windows which arrived Thursday and these porch timbers which are getting mortised and tenoned for assembly. tgh

July 28, 2008

Water and steel

Filed under: Senior Residence — knewman @ 9:22 pm

After seven days allowing the concrete to cure, the steel arrived for erection.

 

The lower beams border the vaulted ceiling of the Great Room.  The high beam is the ridge.

 

The wall framing arrives in prebuilt sections.  It should take only two days to raise the walls.

On Wednesday the drilling crew arrived for the water well.  By Thursday they had finished drilling – final depth 385′.

 

 Friday the casing was inserted and cemented in and Monday the screen was installed.

 

Drilling part is done, now we just need plumbing and power.  tgh